Selected development signals
01Planning and zoning
200 MW data center at Schladen-Werla
MarketGermanyLocationBeuchte · Lower SaxonyStageplanning procedure
Summarygdd is developing a large data-center site on more than 140,000 m². Following the planning-initiation resolution, land-use planning and technical definition are continuing.
Developer relevanceNamed pre-construction site with an active planning procedure and clear technical follow-up checks. A developer statement on grid reservation still requires technical and contractual verification.
Next check: Review the planning timetable, site control, bankable grid connection, cooling, heat reuse and operator concept in the data room.
02Spatial-planning review
Proposed data-center site at Zistersdorf
MarketAustriaAreaapproximately 14 haStageearly site review
SummaryThe municipality confirms a potential data-center area north-east of Zistersdorf. Spatial-planning requirements are being reviewed; no specific permit application has yet been filed.
Developer relevanceVery early publicly identified site, leaving decisions open on suitability, special zoning, technical design and the permitting route.
Next check: Clarify zoning requirements, option rights, contamination, ecology, grid route, heat offtake and cooling concept.
03Building application
ENKA data center at Beringen
MarketSwitzerlandLocationBeringen · SchaffhausenStagepublic consultation
SummaryA planning application covers demolition of an existing warehouse and construction of two data-center buildings, offices, backup generation, photovoltaic systems and electrical service buildings.
Developer relevanceSpecific pre-construction project. The outstanding building permit is the decisive next development gate; no project-specific grid connection is publicly confirmed.
Next check: Complete consultation and permitting, address objections and official conditions, then decide on project execution.