Debt and project-finance opportunity seeking EUR 4m to complete Phase 1 infrastructure and deploy equipment for a permitted data center project in Burgas, Bulgaria.
The current project information describes a 1,200 sqm data center building on a 2,000 sqm regulated plot, with 2.5 MW of secured power at 20 kV. Phase 1 is designed for approximately 200 racks and 1.2–1.6 MW of useful IT load.
Completion financing for infrastructure and equipment deployment.
2.5 MW secured power connection at 20 kV.
Approximately 200 racks with high-density zones of up to 15 kW per rack.
Adjacent 7,634 sqm land and a registered 10 MW grid request for a potential Phase 2; additional capacity is not yet secured.
Relevant for private credit, infrastructure debt and specialist data-center lenders able to assess construction completion and equipment financing.
| Metric | Current indication |
|---|---|
| Location | Burgas, Bulgaria |
| Regulated plot | Approx. 2,000 sqm |
| Building | Approx. 1,200 sqm |
| Secured power | 2.5 MW at 20 kV |
| Phase 1 capacity | Approx. 200 racks / 1.2–1.6 MW useful IT load |
| Capital sought | EUR 4m debt / project finance |